May 232013
 

Today the excavator driver made the field ready.
After that he digged me the 9 holes for the guy wire posts. 8 “small” ones and on big one.

DSC00645

We made it sloping from the house to the field

DSC00644

Nice done

 

 

 

 

 

 

DSC00649

water is already in

DSC00646

The bottom is sand and that good

 

May 182013
 

The contracter who is doing the field had problems with the excavator.

The last part of the ditch has been dug and after that the excavator died again.  The contractor brought in another excavator to finish the work. The ditch next to the house is now almost closed.  Some other work has to be done. Hopefully this will be ready after the weekend.

DSC00641

Excavator is front replaces broken crane in the back

DSC00628

View to the field from the house

DSC00631

Excavator is broken. Work on hold.

DSC00629

Ditch finally closed.

 

May 072013
 

The land consolidation people started to organize a new dam sot hat i can enter the filed closer by my house.. They also started to dig the ditch round the field and a last they will close the ditch between the house and the field.

DSC00584sm

Drain pipes for under the dam.

DSC00597sm

Dam is filled with the drain pipes and sand.

 

 

 

 

 

 

DSC00616

New ditch and a lot of sand.

DSC00612

Only a few meters to go. But next day the excavator would not start up again.

 

 

Apr 142013
 

Finally the cadastral survey people where here. Now I now exact what the new borders from the new property are and now I can start to figure out the positions off the new towers.

 

Apr 102013
 

Last 2 meter contest we had some problems with the audio from the 144mhz pc. We could play our wav files after a while but the sound cards did not allow to record the contest with the ne separate program (qsorder) for N1mm. I put an other extra sound card (tks PA1M) in and now it is working fine.